Jal Jeevan Mission - District Dashboard  - Deoria

       
Heirarchy / District Progress Reference
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ Villages:
Total Certified :
Handed Over Villages :
GP level member :
VWSC/ Pani Samiti/ Water User Group :
Operation and Maintenance User :
Women identified for field test kit (FTK) testing :
Skilled Human Resources available in village :
UP Jal Nigam Old Scheme
Total Scheme :
Total Village :
Total OHT :
Schemes send to O&M Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Partial Complete Schemes Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Incoming Complaints/Feedback Received
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken Details
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Total Pradhan Call Feedback
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
S.E.,(Division), Jal Nigam (Rural) Feedback Taken
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (Zone), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (H.O.), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Unit Co-ordinator (Technical), SWSM
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
ISA Activities
Total ISA Activities :
Total Photos Uploaded :
Total Videos Uploaded :
IEC Activities
WorkShop/Wall Writing Activities :
PHASE II Activity :
IEC Regional Language Activity :
IEC Outdoor Activities :
JJM Scheme Details Phase 1       Phase 2,3,5       Phase 4
Total JJM Scheme :
Total JJM Scheme Covered Village :
O&M Schemes
O&M Schemes:
O&M JJM Village :
O&M Schemes Integrate With Automation :
Automation Integrated Schemes
Automation Installed Scheme:
Integrated Scheme :
Integrated OHT :
Integrated Village :
Live Connected OHT :
Live Pump On OHT :
Last 2 days Water Not Supply OHT :
Regular Water Supply OHT :
Water supply less than 75% percent :
Water supply greater than 150% percent :
Automation Integrated Verified Schemes (EE E&M)
Integrated Scheme :
Integrated OHT :
Integrated Village :
Functional OHT Water Demand/Supply (Meter 3)
Water Demand Daily :
Water Demand Weekly :
Water Demand Monthly :
Water Supply Daily :
Water Supply Weekly :
Water Supply Monthly :
Automation Integrated SchemesReference
Sno. Scheme Status Pump Status Scheme Id Scheme Name Agency Name Covered Village Regular Water Supply Last Data Receive Date
Total 13 10
1 8359897 Balpur Shrinagar G.P. water Supply Scheme Gayatri Projects LTD 2 2 02-08-2025 12:11 PM
2 8359958 Siswan G.P Water Supply Scheme Gayatri Projects LTD 1 0 02-08-2025 12:11 PM
3 8360439 Mirjapur GP Water Supply Scheme LC INFRA 1 1 02-08-2025 12:04 PM
4 8361750 MISHRAULI DIXIT GP WATER SUPPLY SCHEME LC INFRA 1 1 02-08-2025 11:54 AM
5 8361815 BANKATA SHAMBHU LC INFRA 2 2 02-08-2025 12:12 PM
6 8389685 Pargasha GP Water Supply Scheme LC INFRA 2 2 02-08-2025 12:12 PM
7 20000646 Sohanipar Gram Panchayat Water Supply Scheme. Gayatri Projects LTD 1 1 02-08-2025 12:11 PM
8 20000688 Deoghat Gram Panchayat Water Supply Scheme. Gayatri Projects LTD 1 1 02-08-2025 12:11 PM
9 20000714 Mathia Khurd Gram Panchayat Water Supply Scheme Gayatri Projects LTD 1 0 02-08-2025 12:11 PM
10 20013060 DEOGAON GP WATER SUPPLY SCHEME LC INFRA 1 0 02-08-2025 12:04 PM
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 804 792 98.51
2 Pump House 804 775 96.39
3 Chlorination system 259 233 89.96
4 OHT 776 762/341 98.20
5 Distribution (Line Laying in Km.) 7534 6828 90.63
6 Solar Plant 702 511 72.79
7 F.H.T.C. 432496 424367 98.12
9 ROAD DISMENTLING/RESTORATION(KM) 2112 2053 97.21
10 Villages where 100 % road restoration completed 97070 60333 62.15
11 Comissioning of Village 1508 679 45.03
12 Regular water supply 1508 648 42.97
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Gayatri Projects LTD 217 327 80002 78754 98.44% 233 43
2 LC INFRA 365 720 154614 152217 98.45% 463 131
3 Rithwik-Koya (JV) 213 461 69831 67155 96.17% 110 44
4 UNIVERSAL MEP 69 118 22593 20999 92.94% 48 16
Total 864 1626 327040 319125 97.58% 854 234