Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in

Jal Jeevan Mission - Farrukhabad

Table 1 Physical Progress Phase wise
Sno Agency Name Total
Schemes
Total
Villages
RWS Villages Work Completed Work In Progress Villages
in O&M
but not RWS
OHT
Total
RWS
Villages
100%
90% to 99%
< 90%
O&M
Schemes
Villages
Trial Run
Schemes
Villages
Schemes
Villages
Direct Pumping
Schemes
Villages
No RWS
Schemes
Villages
Required OHT Completed OHT
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 GVPR 227 402 236 56
22
158
4
4
32
47
191
351
106
144
89
166
0 227 59
2 Vindhya-GAJA (JV) 151 322 288 250
4
34
97
201
30
62
24
59
0
0
15
34
0 154 151
3 Hetvi Construction 84 120 57 10
3
44
0
0
0
0
0
0
0
0
0
0
0 0 0
Total 462 844 581 316
29
236
101
205
62
109
215
410
106
144
104
200
0 381 210


Table 2 RWS disruption(Village)
SNo. Agency Name Total RWS disruption(Village) O&M RWS disruption(Village)
Theft Power
Electrical
Issue
Tullu
Pump
Road
Widening
Damage
Village
Internal
Works
Local
Repairing
Total Theft Power
Electrical
Issue
Tullu
Pump
Road
Widening
Damage
Village
Internal
Works
Local
Repairing
Total
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
No RWS disruption found
Table 3 Certification/Jal Arpan/Jal Aklan/RPWSS/Road Restoration
SNo. Agency Name Certification Jal Arpan Jal Aklan RPWSS 100% Road Restoration Villages
1 2 3 4 5 6 7
1 GVPR 61 0 0 0 294
2 Vindhya-GAJA (JV) 158 7 0 0 295
Total 219 7 0 0 589
Table 4 Components Wise Physical Progress
Sr.No. Components Physical Progress
Target Achivement %
1 2 3 4 5
1 Tubewell 423 422 99.76
2 Pump House 423 416 98.35
3 Chlorination system 309 297 96.12
4 OHT 381 379/210 99.48
5 Distribution (Line Laying in Km.) 3541 3520 99.41
6 Solar Plant 351 323 92.02
7 F.H.T.C. 252320 244832 97.03
9 ROAD DISMENTLING/RESTORATION(KM) 1627 1580 97.11
10 Villages where 100 % road restoration completed 588 589 100.00
11 Comissioning of Village 724 566 78.18
12 Regular water supply 724 501 69.20
Table 5 Unified Command and Control System (UCCS)-Automation
SNo. Agency Name Total O&M
Scheme Integrated Live Scheme Integrated Live
1 2 3 4 5 6 7 8
1 GVPR 227 11 7 4 4 2
2 Vindhya-GAJA (JV) 151 115 115 97 97 97
Total 378 126 122 101 101 99
Table 6 Grievance Redressal System
SNo. Agency Name Total Complaint O&M Complaint
Total Close Pending Total Close Pending
1 2 3 4 5 6 7 8
1 GVPR 655 502 153 13 8 5
2 Vindhya-GAJA (JV) 478 367 111 378 284 94
Total 1133 869 264 391 292 99
Table 7 Water Quality [Comming Soon]
Table 8 Automation Integrated SchemesReference
Sno. Scheme Status Pump Status Scheme Id Scheme Name Agency Name Covered Village Regular Water Supply Last Data Receive Date
Total 22 21
1 20074585 REHA KARANPUR MVS Vindhya-GAJA (JV) 4 4 03-04-2026 09:16 AM
2 20075209 BIRAHAMPUR JAGIR,RASHIDABAD DARAPUR MVS Vindhya-GAJA (JV) 3 3 03-04-2026 09:16 AM
3 20076924 GUDERA SVS Vindhya-GAJA (JV) 1 1 03-04-2026 09:16 AM
4 20080822 LALPURPATTI SVS Vindhya-GAJA (JV) 1 1 03-04-2026 09:16 AM
5 20080827 BHAUPUR CHAURASI SVS Vindhya-GAJA (JV) 1 1 03-04-2026 09:16 AM
6 20081341 GANGAICH & NARAINPUR MVS Vindhya-GAJA (JV) 2 2 03-04-2026 09:16 AM
7 20091265 BARAKASUR URF RANIGARH Vindhya-GAJA (JV) 2 1 03-04-2026 09:16 AM
8 20091728 SHERPUR SARAI MVS Vindhya-GAJA (JV) 2 2 03-04-2026 09:16 AM
9 20092017 JARHARI MVS Vindhya-GAJA (JV) 2 2 03-04-2026 09:16 AM
10 20092383 BEG & HUSAINPUR BANGER MVS Vindhya-GAJA (JV) 4 4 03-04-2026 09:16 AM
Department Contact Number
S.No. Name Designation Monile No.
1 SAJAN KUMAR Executive Engineer
2 Farrukhabad DM 9454417552
3 Akhilesh Kumar JE 7985456740
4 ANKUR SAXENA JE 8960106195
5 veekesh kumar JE 7905636370
6 Farrukhabad EE E AND M 9473942740
DWSM Minutes of Meeting
S.No. DWSM MOM Date Subject Attachment
1 24-Jul-2025 DWSM MEETING
2 03-May-2025 DWSM MEETING
3 18-Feb-2025 DWSM MEETING
4 20-Nov-2024 DWSM MEETING
5 08-Oct-2024 DWSM MEETING
6 22-Jul-2024 DWSM MEETING
7 28-Jun-2024 DWSM MEETING
8 07-Jun-2024 DWSM MEETING
9 15-Mar-2024 DWSM meeting
10 22-Feb-2024 DWSM MEETING
11 27-Sep-2023 DWSM meeting
12 26-Jul-2023 DWSM meeting
13 25-May-2023 DWSM MEETING
14 13-Mar-2023 DWSM meeting
15 24-Feb-2023 DWSM meeting
16 08-Feb-2023 DWSM meeting
17 06-Dec-2022 DWSM meeting
18 15-Nov-2022 DWSM meeting
19 13-Oct-2022 DWSM meeting
20 07-Sep-2022 DWSM meeting