Jal Jeevan Mission-District Dashboard

Heirarchy / District Progress
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Scheme Details
JJM Scheme :
JJM Village :
Jal Nigam Scheme :
Jal Nigam Village :
JJM + Jal Nigam Scheme :
JJM + Jal Nigam Village :
Village Status
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
NGO :
NTD :
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 GA INFRA - BABA (JV) 67 122 43771 39314 89.82% 58 6
2 Gayatri Projects LTD 170 325 91012 89333 98.16% 265 74
3 Power Mech Projects Ltd 425 733 243046 200378 82.44% 364 55
Total 662 1180 377829 329025 87.08% 687 135
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 705 701 99.43
2 Pump House 705 700 99.29
3 Chlorination system 194 177 91.24
4 OHT 665 660/398 99.25
5 Distribution (Line Laying in Km.) 7824 7704 98.47
6 Solar Plant 520 468 90.00
7 F.H.T.C. 434167 381744 87.93
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 4923 4728 96.04
10 Villages where 100 % road restoration completed 97064 59331 61.13
11 Comissioning of Village 1180 402 34.07
12 Regular water supply 1180 386 32.71
;