Jal Jeevan Mission - District Dashboard  - Prayagraj

       
Heirarchy / District Progress Reference
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ Villages:
Total Certified :
Handed Over Villages :
GP level member :
VWSC/ Pani Samiti/ Water User Group :
Operation and Maintenance User :
Women identified for field test kit (FTK) testing :
Skilled Human Resources available in village :
UP Jal Nigam Old Scheme
Total Scheme :
Total Village :
Total OHT :
Schemes send to O&M Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Partial Complete Schemes Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Incoming Complaints/Feedback Received
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken Details
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Total Pradhan Call Feedback
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
S.E.,(Division), Jal Nigam (Rural) Feedback Taken
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (Zone), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (H.O.), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Unit Co-ordinator (Technical), SWSM
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
ISA Activities
Total ISA Activities :
Total Photos Uploaded :
Total Videos Uploaded :
IEC Activities
WorkShop/Wall Writing Activities :
PHASE II Activity :
IEC Regional Language Activity :
IEC Outdoor Activities :
JJM Scheme Details Phase 1       Phase 2,3,5       Phase 4
Total JJM Scheme :
Total JJM Scheme Covered Village :
O&M Schemes
O&M Schemes:
O&M JJM Village :
O&M Schemes Integrate With Automation :
Automation Integrated Schemes
Automation Installed Scheme:
Integrated Scheme :
Integrated OHT :
Integrated Village :
Live Connected OHT :
Live Pump On OHT :
Last 2 days Water Not Supply OHT :
Regular Water Supply OHT :
Water supply less than 75% percent :
Water supply greater than 150% percent :
Automation Integrated Verified Schemes (EE E&M)
Integrated Scheme :
Integrated OHT :
Integrated Village :
Functional OHT Water Demand/Supply (Meter 3)
Water Demand Daily :
Water Demand Weekly :
Water Demand Monthly :
Water Supply Daily :
Water Supply Weekly :
Water Supply Monthly :
Automation Integrated SchemesReference
Sno. Scheme Status Pump Status Scheme Id Scheme Name Agency Name Covered Village Regular Water Supply Last Data Receive Date
Total 10 9
1 Off 8360353 RAINI GRAM PANCHAYAT WATER SUPPLY SCHEME Larsen & Toubro Ltd 1 1 02-08-2025 12:10 PM
2 Off 8361286 SEMRA MULTI VILLAGES WATER SUPPLY SCHEME Larsen & Toubro Ltd 2 1 02-08-2025 12:10 PM
3 Off 8361288 SARAI RAHIYA MULTI VILLAGES WATER SUPPLY SCHEME Larsen & Toubro Ltd 2 2 02-08-2025 12:10 PM
4 Off 8388580 Babahan Kuseyan Gram Panchayat Larsen & Toubro Ltd 2 2 02-08-2025 12:10 PM
5 Off 20016376 DAYALPUR VILLAGE WATER SUPPLY SCHEME Larsen & Toubro Ltd 3 3 02-08-2025 12:10 PM
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 664 643 96.84
2 Pump House 664 643 96.84
3 Chlorination system 224 212 94.64
4 OHT 850 726/230 85.41
5 Distribution (Line Laying in Km.) 18243 16438 90.11
6 Solar Plant 542 331 61.07
7 F.H.T.C. 651466 490804 75.34
9 ROAD DISMENTLING/RESTORATION(KM) 5469 5404 98.81
10 Villages where 100 % road restoration completed 97070 60333 62.15
11 Comissioning of Village 1338 422 31.54
12 Regular water supply 1338 412 30.79
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Larsen & Toubro Ltd 664 1338 336258 320419 95.29% 495 237
2 VPRPL 1 310 59728 13796 23.10% 29 25
3 GAJA - GAIPL JV 1 532 112237 20409 18.18% 52 36
Total 666 2180 508223 354624 69.78% 576 298