| Sno | Agency Name | Total Schemes |
Total Villages |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS |
OHT | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total RWS Villages |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | Larsen & Toubro Ltd | 1 | 673 | 0 | 000 | 0 0 | 0 0 | 1 673 | 00 | 1673 | 0 | 249 | 0 |
| 2 | NCC Ltd. | 1 | 2 | 0 | 000 | 0 0 | 0 0 | 1 2 | 00 | 12 | 0 | 0 | 0 |
| 3 | Dara Engineering | 86 | 106 | 0 | 000 | 0 0 | 0 0 | 0 0 | 00 | 00 | 0 | 0 | 0 |
| Total | 88 | 781 | 0 | 0 0 0 | 0 0 | 0 0 | 2 675 | 0 0 | 2 675 | 0 | 249 | 0 | |
| SNo. | Agency Name | Total RWS disruption(Village) | O&M RWS disruption(Village) | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| SNo. | Agency Name | Certification | Jal Arpan | Jal Aklan | RPWSS | 100% Road Restoration Villages |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | Larsen & Toubro Ltd | 0 | 0 | 0 | 0 | 7 |
| 2 | NCC Ltd. | 1 | 0 | 0 | 0 | 0 |
| Total | 1 | 0 | 0 | 0 | 7 | |
| Sr.No. | Components | Physical Progress | ||
|---|---|---|---|---|
| Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 |
| 4 | OHT | 249 | 247 | 99.20 |
| 5 | Distribution (Line Laying in Km.) | 6914 | 3882 | 56.15 |
| 7 | F.H.T.C. | 282949 | 86543 | 30.59 |
| 9 | ROAD DISMENTLING/RESTORATION(KM) | 511 | 438 | 85.71 |
| 10 | Villages where 100 % road restoration completed | 7 | 7 | 100.00 |
| SNo. | Agency Name | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Larsen & Toubro Ltd | 1 | 0 | ||||
| 2 | NCC Ltd. | 1 | 0 | ||||
| Total | 2 | 0 | |||||
| SNo. | Agency Name | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | NCC Ltd. | 2 | 1 | 1 | 0 | ||
| 2 | Larsen & Toubro Ltd | 345 | 297 | 48 | 0 | ||
| Total | 347 | 298 | 49 | 0 | |||
| Sno. | Scheme Status | Pump Status | Scheme Id | Scheme Name | Agency Name | Covered Village | Regular Water Supply | Last Data Receive Date |
| S.No. | Name | Designation | Monile No. |
|---|---|---|---|
| 1 | Devendra Kumar Singh | Executive Engineer | 9473942636 |
| 2 | Firozabad | DM | 9454417510 |
| 3 | Sandeep Verma | JE | 9517512879 |
| 4 | Krishn Dev Singh | JE | 9412633681 |
| 5 | Rajendra Kumar | JE | 6397639248 |
| 6 | Ram Avtar | JE | 7251043070 |
| 7 | Sandesh Kardam | JE | 7351721991 |
| 8 | Sandeep Verma | JE | 9517512879 |
| 9 | Pradeep Kumar | JE | 6396346395 |
| 10 | Firozabad | EE E AND M |