| Sno | Agency Name | Total Schemes |
Total Villages |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS |
OHT | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total RWS Villages |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | KLSR - RAYS (JV) | 142 | 297 | 70 | 91942 | 3 5 | 4 7 | 135 285 | 2754 | 105224 | 0 | 142 | 15 |
| 2 | Larsen & Toubro Ltd | 779 | 1264 | 542 | 186108248 | 84 132 | 87 143 | 608 1000 | 184302 | 454727 | 0 | 759 | 197 |
| 3 | Vindhya Telelinks Limited | 152 | 254 | 158 | 1713128 | 0 0 | 0 0 | 0 0 | 00 | 00 | 0 | 0 | 0 |
| Total | 1073 | 1815 | 770 | 212 140 418 | 87 137 | 91 150 | 743 1285 | 211 356 | 559 951 | 0 | 901 | 212 | |
| SNo. | Agency Name | Total RWS disruption(Village) | O&M RWS disruption(Village) | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| 1 | KLSR - RAYS (JV) | 0 | 0 | 0 | 3 | 0 | 0 | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2 | Larsen & Toubro Ltd | 0 | 0 | 0 | 0 | 16 | 0 | 16 | 0 | 0 | 0 | 0 | 10 | 0 | 10 |
| Total | 0 | 0 | 0 | 3 | 16 | 0 | 19 | 0 | 0 | 0 | 0 | 10 | 0 | 10 | |
| SNo. | Agency Name | Certification | Jal Arpan | Jal Aklan | RPWSS | 100% Road Restoration Villages |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | KLSR - RAYS (JV) | 11 | 0 | 0 | 0 | 233 |
| 2 | Larsen & Toubro Ltd | 156 | 2 | 0 | 0 | 846 |
| Total | 167 | 2 | 0 | 0 | 1079 | |
| Sr.No. | Components | Physical Progress | ||
|---|---|---|---|---|
| Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 917 | 865 | 94.33 |
| 2 | Pump House | 917 | 878 | 95.75 |
| 3 | Chlorination system | 371 | 327 | 88.14 |
| 4 | OHT | 901 | 893/212 | 99.11 |
| 5 | Distribution (Line Laying in Km.) | 14503 | 10269 | 70.81 |
| 6 | Solar Plant | 752 | 549 | 73.01 |
| 7 | F.H.T.C. | 510687 | 495586 | 97.04 |
| 9 | ROAD DISMENTLING/RESTORATION(KM) | 1116 | 997 | 89.34 |
| 10 | Villages where 100 % road restoration completed | 1079 | 1081 | 100.00 |
| 11 | Comissioning of Village | 1561 | 594 | 38.05 |
| 12 | Regular water supply | 1561 | 544 | 34.85 |
| SNo. | Agency Name | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | KLSR - RAYS (JV) | 142 | 7 | 3 | 3 | 3 | 1 |
| 2 | Larsen & Toubro Ltd | 779 | 43 | 0 | 84 | 38 | 0 |
| Total | 921 | 50 | 3 | 87 | 41 | 1 | |
| SNo. | Agency Name | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | KLSR - RAYS (JV) | 136 | 132 | 4 | 4 | 4 | 0 |
| 2 | Larsen & Toubro Ltd | 705 | 691 | 14 | 137 | 131 | 6 |
| Total | 841 | 823 | 18 | 141 | 135 | 6 | |
| S.No. | Name | Designation | Monile No. |
|---|---|---|---|
| 1 | mahendra singh | Executive Engineer | 9473942717 |
| 2 | Gonda | DM | 9454417537 |
| 3 | Anuj Kumar | JE | 9473942311 |
| 4 | Saroj Kumar Gupta | JE | 9473942304 |
| 5 | Riyaz Ahmad | JE | 9453515973 |
| 6 | Manish Panday | JE | 9670398839 |
| 7 | Vishal Pathak | JE | 6387637231 |
| 8 | Harshit Mishra | JE | 8318660900 |
| 9 | Sachin Verma | JE | 9794561461 |
| 10 | Ankush Gupta | JE | 9670633910 |
| 11 | Rohan Verma | JE | 7078340420 |
| 12 | GONDA | EE E AND M | 9473942581 |