| Sno | Agency Name | Total Schemes |
Total Villages |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS |
OHT | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total RWS Villages |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | Larsen & Toubro Ltd | 664 | 1341 | 322 | 2831722 | 81 134 | 97 186 | 486 1027 | 4078 | 4821012 | 3 | 662 | 205 |
| 2 | VPRPL | 1 | 276 | 0 | 000 | 0 0 | 0 0 | 1 276 | 00 | 1276 | 0 | 74 | 29 |
| 3 | GAJA - GAIPL JV | 1 | 453 | 0 | 000 | 0 0 | 0 0 | 1 453 | 00 | 1453 | 0 | 115 | 27 |
| 4 | LC Infra Project Limited | 234 | 568 | 524 | 3158435 | 0 0 | 0 0 | 0 0 | 00 | 00 | 0 | 0 | 0 |
| Total | 900 | 2638 | 846 | 314 75 457 | 81 134 | 97 186 | 488 1756 | 40 78 | 484 1741 | 3 | 851 | 261 | |
| SNo. | Agency Name | Total RWS disruption(Village) | O&M RWS disruption(Village) | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| 1 | Larsen & Toubro Ltd | 25 | 3 | 3 | 33 | 0 | 7 | 70 | 1 | 0 | 0 | 4 | 0 | 0 | 5 |
| Total | 25 | 3 | 3 | 33 | 0 | 7 | 70 | 1 | 0 | 0 | 4 | 0 | 0 | 5 | |
| SNo. | Agency Name | Certification | Jal Arpan | Jal Aklan | RPWSS | 100% Road Restoration Villages |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | Larsen & Toubro Ltd | 238 | 4 | 0 | 0 | 885 |
| 2 | VPRPL | 0 | 0 | 0 | 0 | 0 |
| 3 | GAJA - GAIPL JV | 2 | 0 | 0 | 0 | 0 |
| Total | 240 | 4 | 0 | 0 | 885 | |
| Sr.No. | Components | Physical Progress | ||
|---|---|---|---|---|
| Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 664 | 643 | 96.84 |
| 2 | Pump House | 664 | 626 | 94.28 |
| 3 | Chlorination system | 222 | 211 | 95.05 |
| 4 | OHT | 851 | 733/261 | 86.13 |
| 5 | Distribution (Line Laying in Km.) | 18243 | 16621 | 91.11 |
| 6 | Solar Plant | 542 | 334 | 61.62 |
| 7 | F.H.T.C. | 651699 | 491219 | 75.38 |
| 9 | ROAD DISMENTLING/RESTORATION(KM) | 5462 | 5406 | 98.97 |
| 10 | Villages where 100 % road restoration completed | 885 | 885 | 100.00 |
| 11 | Comissioning of Village | 1341 | 413 | 30.80 |
| 12 | Regular water supply | 1341 | 408 | 30.43 |
| SNo. | Agency Name | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Larsen & Toubro Ltd | 664 | 25 | 0 | 81 | 19 | 0 |
| 2 | VPRPL | 1 | 0 | ||||
| 3 | GAJA - GAIPL JV | 1 | 0 | ||||
| Total | 666 | 25 | 0 | 81 | 19 | 0 | |
| SNo. | Agency Name | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | GAJA - GAIPL JV | 153 | 145 | 8 | 0 | ||
| 2 | VPRPL | 98 | 94 | 4 | 0 | ||
| 3 | Larsen & Toubro Ltd | 1557 | 1515 | 42 | 417 | 414 | 3 |
| Total | 1808 | 1754 | 54 | 417 | 414 | 3 | |
| S.No. | Name | Designation | Monile No. |
|---|---|---|---|
| 1 | Praveen Kutti | Executive Engineer | 9473942662 |
| 2 | Prayagraj | DM | 9454417517 |
| 3 | Anurag Yadav | JE | 9451141800 |
| 4 | Amit Gupta | JE | 8318083443 |
| 5 | Rinkal Chauhan | JE | 9506155456 |
| 6 | Pankaj Kumar | JE | 7618967016 |
| 7 | Roman Ansari | JE | 9721177317 |
| 8 | Brijesh Kumar | JE | 9936484945 |
| 9 | Mahendra Pratap Singh | JE | 8317076570 |
| 10 | Niranjan Kumar Verma | JE | 8931812919 |
| 11 | Upendra Kumar Gond | JE | 9628809278 |
| 12 | Prayagraj | EE E AND M | 9473942669 |